C-Series Project

Theme
Offshore
Client
ONGC, India
Status
Completed, 2006 - 2009 ( 32 Months )
Contract Type
EPC
Contract Value
388.19
Scope Of Work

Design, Engineering, Procurement, Fabrication, Load out, Tie-down/Sea fastening, Tow-out/Sail-out Transportation and installation of 4 new Well Platforms, Anti-corrosion & Weight Coating, Laying of Submarine Pipelines - Submarine P/Ls (8", 22", 28" - 180 KM) , Modifications on existing Platform NQG, Hook-up, Testing, Pre-Commissioning, Commissioning (wherever applicable).