Go Back
#50/9055

EPC for Bab Thammama "G" and Habshan - 2 Development 1.8 MMBOPD Project

Theme
Onshore
Client
ADCO, Abu Dhabi, UAE
Status
Completed, 2010 - 2013 ( 47 Months )
Contract Type
EPC
Contract Value
632.48
Scope Of Work

EPC Project for Bab Thammama G and Habshan 2 onshore oil fields, consisting of the following facilities:

  • 639 Km of Pipelines including transfer lines, flow lines & water Injection lines.
  • 4 new Remote Degassing Stations (RDS)/Transfer Lines with 54 new Prod. Wells and Flow lines.
  • 8 new Water Injection Clusters (WIC) with 52 new WI Wells, Headers and Injection lines.
  • Modification Works at Bab Central Degassing Stn. (BCDS) and 33kV OH lines to all new facilities (67km).