Go Back
#14/2207

Umm Lulu Full Field Development Project (Pkg-1)

Theme
Offshore
Client
ADMA OPCO, UAE
Status
Completed, 2013 - 2021 ( 96 Months )
Contract Type
EPC
Scope Of Work

EPC Works covering:

  • 7 Jackets (6 for Well Head Towers & 1 Riser Platform).
  • 6 Topsides for Well Head Towers (WHT-1, WHT-2, WHT-3, WHT-5, WHT-7 & WHT-8)
  • 2 Nos Well head towers modification (WHT-4 & WHT-6)
  • 25 Nos. In-field pipe lines (18”, 16”, 10”, 8” & 6” – 85.1 Kms) between Well Head Towers & UL Riser Platform.
  • 1 No. 20” MOL pipeline from Umm Lulu Riser Platform to KP 34.8 (near S1) – 90 Kms
  • 1 No. FOC Cable Piggy backed with MOL from UL Riser Platform to SARB-S1 Riser Tower