#36/2208
Umm Lulu Full Field Development Project (Pkg-2)

- Theme
- Offshore
- Client
- ADMA OPCO, UAE
- Status
- Completed, 2013 - 2020 ( 90 Months )
- Contract Type
- EPC
Scope Of Work
Detailed Design and Engineering, Procurement, Fabrication, transportation, Surveys, Installation of Facilities, Hook-up/Pre-commissioning and Commissioning upto Ready For Start-up (RFSU), Start-up Assistance and Final Commissioning of 6 New Platforms, Two Flares, Four Bridge Supports and Eleven Bridges and Ten Infield Composite Power & FOC Cables (approx. 38 Km). Decommissioning & Mothballing of a 12" Trunkline.